The electricity generated from each turbine is transmitted via underground and above ground cabling to a central cable marshalling point at the onsite substation, which is located next to the 220kv power line that runs through the site area. The substation then connects directly into the grid network on site.

Preparatory works for the substation site commenced on 16th November 2009 and was completed in April 2010.